After the preliminary consultation, complete and submit Connection Impact Assessment Application. Instructionson how to complete Connection Impact Assessment Application.
Study Agreement
After we review the Connection Impact Assessment Application, you will need to submit a signed Study Agreement along with payment for the Connection Impact Assessment.
Connection Impact Assessment Fee
PUC will perform an estimate once the Preliminary Consultation is complete. Estimated fees are noted below; fees will be communicated and discussed prior to proceeding with the project. Application timelines are typically processed within 60 days; however large projects may be longer.
DER Classification
|
Rating
|
Estimated Cost
|
Small
|
(a) ≤ 500kW connected on distribution system voltage < 15 kV
|
$8,500 plus HST
|
(b) ≤ 1 MW connected on distribution system voltage ≥ 15 kV
|
Mid-Sized
|
(a) ≤ 10 MW but > 500 kW connected on distribution system voltage < 15 kV
|
$15,500 plus HST
|
(b) > 1 MW connected on distribution system voltage ≥ 15 kV
|
Large
|
> 10 MW
|
$25,500 plus HST
|
Simplified
|
For any size simplified CIA
|
$1,000 plus HST
|
Refund timelines are generally within 180 days based on project completion but may extend beyond that for large projects.
Connection Impact Assessment
We will conduct a Connection Impact Assessment and issue a report. You will be allocated capacity on the grid upon completion of the Connection Impact Assessment by PUC and Hydro One (if applicable). Generally, this process takes 60-75 days, but in some situations, a cost estimate timeline extension may be required for a project that meets the criteria specified in section 5.9.1 of the OEB DERCP.
Note: For generators connecting on a Hydro One shared feeder, Hydro One will be required to perform its own Connection Impact Assessment.